Monthly Report – August 2021

Monthly Report – August 2021

In August, a contract was signed with Autland Heavy Equipment for road and slope stabilisation works in Long Trench, and works have begun. At the Zion Hill Reservoir site, the existing structure has been demolished, concrete casting of the tank footing and anchors...
Monthly Report – July 2021

Monthly Report – July 2021

    In July, a contract was signed with Tortola Paving Ltd. for Asphaltic Works for the six completed road rehabilitation and slope stabilization sites. Demolition work on the Zion Hill Reservoir project was completed in July, paving the way for installation...
Monthly Report – June 2021

Monthly Report – June 2021

  In June, works were completed at the Ballast Bay and Great Mountain 2 road rehabilitation sites, bringing the total number of completed road project activities to six (6). Completion of the first six (6) road works sites has paved the way for work to begin on...