by Colene Penn | Oct 12, 2021 | Monthly Reports, Publications
In August, a contract was signed with Autland Heavy Equipment for road and slope stabilisation works in Long Trench, and works have begun. At the Zion Hill Reservoir site, the existing structure has been demolished, concrete casting of the tank footing and anchors...
by Colene Penn | Sep 15, 2021 | Monthly Reports, Publications
In July, a contract was signed with Tortola Paving Ltd. for Asphaltic Works for the six completed road rehabilitation and slope stabilization sites. Demolition work on the Zion Hill Reservoir project was completed in July, paving the way for installation...
by Colene Penn | Aug 16, 2021 | Monthly Reports, Publications
In June, works were completed at the Ballast Bay and Great Mountain 2 road rehabilitation sites, bringing the total number of completed road project activities to six (6). Completion of the first six (6) road works sites has paved the way for work to begin on...
by Colene Penn | Jul 19, 2021 | Monthly Reports, Publications
In May, the rubberized court surface for the outdoor court of the Jeffrey Caines Arena in Virgin Gorda was completed. Final works on both the Carrot Bay and Long Bush Reservoir sites were also completed in May, which will facilitate more reliable water...
by Colene Penn | Jun 25, 2021 | Monthly Reports, Publications
In April, the rubberized court surface on the Anegada Recreation Facility was completed, and final works on the Carrot Bay Reservoir site neared completion. Practical completion is expected to be reached on four of the first six Road Rehabilitation sites by May...
by Colene Penn | May 13, 2021 | Monthly Reports, Publications
In March, the Flax Administration Building on Virgin Gorda reached practical completion and was handed over to the Deputy Governor’s Office, marking completion of the second of three VG Admin Buildings to be completed under the Caribbean Development Bank’s...