FISH BAY PROJECT CONTINUES WITH WATER PIPELINE UPGRADES
Now that 65% of the concrete pours are completed, the works at Fish Bay will focus on the water pipeline upgrades which have already commenced.
Now that 65% of the concrete pours are completed, the works at Fish Bay will focus on the water pipeline upgrades which have already commenced.
Background: The Virgin Islands Recovery and Development Agency (RDA) has contracted firms for the construction of the Elmore Stoutt High School (ESHS) under the ESHS Redevelopment project. Construction has started on 4th April 2022, and this requires construction materials and finishes to be available in the territory for use by the selected contractors. The RDA…
The full depth road reconstruction on the Fish Bay Road is scheduled to commence on Monday, 16 May, 2022 and traffic disruption is expected.
In May 2022, work continued across ongoing RDA-implemented projects. Specifically in May, work continued in earnest on the Redevelopment of the Elmore Stoutt High School, with block wall construction for the first floors of the classroom blocks completed, and work having begun on the second floors.
Winning Tenderer: Traders Choice Limited Commencement Date of Contract: 28th April 2022 Sector: Resilient InfrastructureType: Works
The Virgin Islands Recovery and Development Agency (RDA) has contracted firms for the construction of the Elmore Stoutt High School (ESHS) under the ESHS Redevelopment project. Construction has started on 4th April 2022, and this requires construction materials and finishes to be available in the territory for use by the selected contractors. The RDA now…