MONTHLY REPORT – April 2023
In April 2023, initial planning continued on projects recently assigned to the RDA, including the Trellis Bay Welcome Centre, the Agriculture and Fisheries Complex and Farmers Reservoir, and the National Cultural Centre, Archives, Library and Museum (Heritage Village). Statements of Requirement are being prepared, finalised and signed-off for these three projects. . Works continued on the Joint Marine Shore Base, with the old building completely demolished, and formwork and concrete pouring for the foundation of the new building completed in April. This project is on-track to be completed in the first quarter of 2024.