MONTHLY REPORT – July 2023
In July 2023, works on the Jost Van Dyke (JVD) Multipurpose Educational Facility continued, with completion of works on the roof, including the parapet wall and the timber roof covering the courtyard, as well as most of the required plastering work. Internal mechanical, electrical and plumbing (MEP) works, painting, and other finishings are ongoing. Due to delays in receiving required building materials, this project is now scheduled to be completed by the end of October 2023. Works continued on the Joint Marine Shore Base in July, with concrete poured for the second-floor roof, and second floor columns, windows- and doors-framing as well as MEP works completed.