MONTHLY REPORT – October 2023
In October 2023, a community meeting was held for the Construction of Eslyn Henley Richiez Learning Centre, following the construction contract signing in late August and the completion of demolition works in September. The community meeting was held to display project designs and inform the public of expected construction times and requirements. This project is scheduled to be completed by March 2025. Works continued on the Joint Marine Shore Base building in October, with the installation of windows, drywall partitions, wall tiles, and the wastewater treatment system completed.