MONTHLY REPORT – March 2024
In March 2024, the Virgin Islands Law Enforcement Marine Base project progressed to 96% completion despite delays in shipment of some specialist supplies. Permanent power and water connections were installed at the Marine Base, facilitating expected achievement of practical completion. For other projects, such as the Virgin Islands Agriculture and Fisheries Complex, a Request for Expressions of Interest (REOI) was issued for a design consultant, with a tender deadline of April 8, 2024. For the Farmers Reservoir Paraquita Bay, the procurement process for design consultant services continued with a deadline of April 19, 2024.