Marine Base
MARINE BASE STATUS: COMPLETED Ministry Partner: Governor’s Group Project Number: 177 Project Start Date: 1 May 2019 Projected End Date: 29 March 2024 Duration: 58 months Design Consultant: Trojan Design and Development Ltd. Contractor: James Todman Construction Ltd. Budget: To be released once planning has been finalized Funding Source: BVI & UK Government BACKGROUND Police and customs…