Rehabilitation And Reconstruction Loan – Hurricane Irma Asphaltic Concrete Works For Six Sites
Winning Tenderer: Tortola Paving LtdCommencement Date of Contract: 26th July 2021 Sector: Resilient InfrastructureType: Works
Winning Tenderer: Tortola Paving LtdCommencement Date of Contract: 26th July 2021 Sector: Resilient InfrastructureType: Works
In June, works were completed at the Ballast Bay and Great Mountain 2 road rehabilitation sites, bringing the total number of completed road project activities to six (6). Completion of the first six (6) road works sites has paved the way for work to begin on…
In May, the rubberized court surface for the outdoor court of the Jeffrey Caines Arena in Virgin Gorda was completed. Final works on both the Carrot Bay and Long Bush Reservoir sites were also completed in May, which will facilitate more reliable water…
In April, the rubberized court surface on the Anegada Recreation Facility was completed, and final works on the Carrot Bay Reservoir site neared completion. Practical completion is expected to be reached on four of the first six Road Rehabilitation sites by May…
TENDER SUBMISSION DEADLINE: Wednesday, 9 June, 2021 at 10:00 AM
In March, the Flax Administration Building on Virgin Gorda reached practical completion and was handed over to the Deputy Governor’s Office, marking completion of the second of three VG Admin Buildings to be completed under the Caribbean Development Bank’s…
The Recovery Development Agency (RDA) is accepting bids for three upcoming projects. The projects will be financed by the Government of the Virgin Islands through the Caribbean Development Bank Rehabilitation and Reconstruction Loan and bids are invited for the following: Bids for the Fish Bay Road Rehabilitation Project must be submitted by 10:00 a.m. on…