Bob’s Gas Station – Slope Stabilization and Road Rehabilitation Project, Tortola, BVI
Winning Tenderer: Caribbean Environmental Restoration Ltd Commencement Date of Contract: 29th October 2020 Sector: Resilient InfrastructureType: Works
Winning Tenderer: Caribbean Environmental Restoration Ltd Commencement Date of Contract: 29th October 2020 Sector: Resilient InfrastructureType: Works
Winning Tenderer: Caribbean Environmental Restoration Ltd Commencement Date of Contract: 29th October 2020 Sector: Resilient InfrastructureType: Works
Roads, Slopes & Coastal Defences STATUS: COMPLETED Ministry Partner: Ministry of Transportation, Works, and Utilities Project Number: 180 Project Start Date: August 2020 Projected End Date: COMPLETED Contractors: Autland Heavy Equipment Co. Ltd. Great Mountain I & II, Long Trench, Fish Bay Quality Construction – Hope Hill to Sabbath Hill STO Enterprises & Autland Heavy…
Theodolph Faulkner Administration Building STATUS: DELIVERY UNDERWAY Ministry Partner: Deputy Governor’s Office Project Number: 163 Project Start Date: 1 March, 2021 Project End Date: 16 July, 2021 Duration: 4.5 months Contractor: No Limit Construction Funding Source: BVI Government BACKGROUND The Theodolph Faulkner Administration Building was designed to serve several purposes within the Anegada community. …
Winning Tenderer: Autland Heavy Equipment Co Ltd Commencement Date of Contract: 19th October 2020 Sector: Resilient InfrastructureType: Works
Winning Tenderer: Joint Venture: STO Enterprise/Autland Heavy Equipment Ltd Commencement Date of Contract: 19th October 2020 Sector: Resilient InfrastructureType: Works
Water Network Improvement Reservoirs and Metering STATUS: DELIVERY UNDERWAY Ministry Partner: Ministry of Transportation, Works, and Utilities Project Number: 140 Project Start Date: October 2019 Projected End Date: November 2020 Duration: 13 months Contractor: Autland Heavy Equipment Co. Ltd. Funding Source: BVI Government BACKGROUND Hurricanes Maria and Irma caused damage to the water and sewage…
Bregado Flax Educational Centre STATUS: COMPLETED Ministry Partner: Ministry of Education, Youth Affairs and Sports Project Number: 086 Project Start Date: 22 April 2019 Projected End Date: 26 May 2021 Duration: 25 Months Design Consultant: Trojan Design & Development Ltd. Contractor: Quality Construction Limited Funding Source: Caribbean Development Bank BACKGROUND This project is to undertake…
Halls of Justice STATUS: PLANNING Ministry Partner: Deputy Governor’s Office Project Number: 060 Project Start Date: June 2020 Projected End Date: TBD Duration: TBD Design Consultant: Trojan Design & Development Ltd. Funding Source: Government of the Virgin Islands BACKGROUND This project is focused on the next phase of redevelopment of the Territory’s legal infrastructure, by…
In September 2020, on-site work continued to face some challenges and delays in the first part of September due to curfews and restrictions, work still continued where possible on-site the CDB-funded VG Admin Buildings, Bregado Flax Secondary Building, and the Water and Road Infrastructure projects.