MONTHLY REPORT – November 2023
In November 2023, construction works continued for the JVD Primary School and Joint Marine Shore Base. Other projects such as the West End Ferry Terminal, Agriculture and Fisheries Complex & Farmers’ Reservoir, and the Trellis Bay Welcome Center continued in planning phase. Specifically, for the JVD Primary School, this mainly involved electrical works such as installation of the main electrical distribution system, electrical outlet and switch covers, exit lights and signs. The project is now scheduled to reach substantial completion by the end of December 2023, facilitating anticipated official handover and opening for the school’s Lent term in January 2024. For the Joint Marine Shore Base, installation of windows, drywall partitions, wall tiles and access ramp extension were completed in November.