MONTHLY REPORT – March 2022
In March, contracts were signed with the winning contractors for the Elmore Stoutt High School redevelopment project, with the ongoing CTL relocation phase scheduled to be completed by September of this year.
RDA Monthly Reports
In March, contracts were signed with the winning contractors for the Elmore Stoutt High School redevelopment project, with the ongoing CTL relocation phase scheduled to be completed by September of this year.
In February 2022, the RDA continued to work in partnership with Central Government in delivering projects from the Recovery to Development Plan. In this vein, please find attached the February 2022 Monthly Report which details project progress. You will notice a…
In January 2022, works continued across ongoing RDA-implemented projects, and practical completion was reached on the Demolition Works for the Elmore Stoutt High School (ESHS). Public meetings were held on the completed designs for the High School buildings,…
In December 2021, contracts were signed for the Rehabilitation of the Elmore Stoutt High School project, a major priority for the Government of the Virgin Islands. A contract signing ceremony was held and contracts were signed for demolition as well as design works…
In November 2021, concrete was poured at the Long Trench road rehabilitation and slope stabilisation site, while the bypass road required for the Fish Bay road rehabilitation site was completed and fully in use allowing for the construction of the required new…
In October, asphaltic works were completed for all six of the initial road and slope stabilisation project sites funded by the CDB RRL loan, namely Great Mountain I and II, Little Dix Hill, Hope to Sabbath Hill, Ballast Bay, and Bob’s Gas Station sites. Work…
In September, the completed Bregado Flax Educational Centre Secondary Division buildings were handed over in a ceremony on Virgin Gorda. Also in September, a community meeting was held in Anegada following substantial completion of the Theodore Faulkner Administration…
In August, a contract was signed with Autland Heavy Equipment for road and slope stabilisation works in Long Trench, and works have begun. At the Zion Hill Reservoir site, the existing structure has been demolished, concrete casting of the tank footing and anchors…
In July, a contract was signed with Tortola Paving Ltd. for Asphaltic Works for the six completed road rehabilitation and slope stabilization sites. Demolition work on the Zion Hill Reservoir project was completed in July, paving the way for installation…
In June, works were completed at the Ballast Bay and Great Mountain 2 road rehabilitation sites, bringing the total number of completed road project activities to six (6). Completion of the first six (6) road works sites has paved the way for work to begin on…