MONTHLY REPORT – DECEMBER 2019
Highlights for December include:– continuing works to near completion of the improvements to Bregado Flax Educational Centre, Virgin Gorda – repair works at the Baths, Virgin Gorda.
RDA Monthly Reports
Highlights for December include:– continuing works to near completion of the improvements to Bregado Flax Educational Centre, Virgin Gorda – repair works at the Baths, Virgin Gorda.
In November, five projects in the planning phase and ten in the operations phase. Five projects have been completed and currently, there are no projects in the procurement phase.
In October, there are six projects in the planning phase, three in the procurement phase and seven in the operations phase. Five projects have been completed.
In September, there are seven projects in the planning phase, four in the procurement phase and five in the operations phase. Five projects have been completed.
In August, there are seven projects in the planning phase, four in the procurement phase and eight in the operations phase. Two projects have been completed.
In July, there are four projects in the planning phase, three in the procurement phase and eight in the operations phase. Two projects have been completed.
In June, there are 5 projects in the planning phase, 5 in the procurement phase, 6 in the operations phase and 2 projects have been completed.
In May, there are 10 projects in the planning phase, 5 in the procurement phase, and 6 in the operations phase.
In April, there are 8 projects in the planning phase, 6 in the procurement phase, and 6 in the operations phase
In March, there are 9 projects in the planning phase, 5 in the procurement phase, and 7 in the operations phase.