- Trellis Bay Welcome Centre: The Trellis Bay Welcome Centre achieved practical completion.
- Road Town Improvement: This project remained in planning phase.
- JVD Pond Restoration: The procurement process was in progress for this project in November 2024. Stakeholder engagement was also conducted which included community visits.
- West End Ferry Terminal: This project continued with contract clarifications requested and responded to by the consultant and the RDA. The deadline for bid submissions is extended to 17th January 2025.
- Road Reconstruction Programme: The Statement of Requirement (SoR) for this project was signed in November 2024 and expressions of interest issued.
- Water Optimization: Training session for the Leak Detection activity commenced with a total of 20 trainees participating.
- Virgin Islands Agriculture and Fisheries Complex: Design consultation sessions were held with stakeholders and other end users.
- Farmers’ Reservoir: The procurement process for this project continued in November 2024.
- Eslyn Henley Richiez Learning Centre: Construction works for this project continued in November 2024.
- Renewable Energy Installations: Stakeholder engagement to decide on the way forward was prominent in November 2024.
- Halls of Justice: The design consultant continued working on the requested changes to the design, and updating cost estimates in line with revisions.
- National Cultural Centre, Archives, Library and Museum: This project remained in planning phase, and it is on hold pending further direction from the client Ministries.
- Waste Management Solutions: This project remained in planning phase, and it is on hold pending further direction from the client Ministries.
- Immigration Detention Centre: Stakeholder engagement continued in November 2024, following the change in Ministry with responsibility for the project.
- BVI Health Services Authority Infrastructure Assessment: With the Statement of Requirement (SoR) for this project in May 2024, the planning process continued with stakeholder engagement in November 2024.