MONTHLY REPORT – September 2024
In September 2024, the procurement process for the West End Ferry Terminal project continued with contract clarifications requested and responded to by the consultant and the RDA. Bidders also continued work on submissions for 25thOctober 2024 deadline. In other projects, such as the Trellis Bay Welcome Centre, construction activities continued such as the concrete pour for the roof slab was completed, alongside completion of the superstructure and external plastering. For the Water Optimization project, the procurement process continued for the Supply and Installation of Water Meters for Reservoirs across the Territory.