Monthly Report – March 2021

Monthly Report – March 2021

  In March, the Flax Administration Building on Virgin Gorda reached practical completion and was handed over to the Deputy Governor’s Office, marking completion of the second of three VG Admin Buildings to be completed under the Caribbean Development Bank’s...
Monthly Report – February 2021

Monthly Report – February 2021

  In February 2021, contracts were signed for the refurbishment of the Anegada Recreation Grounds as well as the Anegada Administration Building and the Road Town Police Station. These contract signatures set the stage for works to begin on these projects. Also...
Monthly Report – JANUARY 2021

Monthly Report – JANUARY 2021

  In January 2021, the first Road project was completed at Great Mountain I, with work continuing on five other project sites across Tortola. Substantial completion was also reached on the Road Town Police Station project based on its original scope. Some...
Monthly Report – December 2020

Monthly Report – December 2020

  In December 2020, substantial completion was achieved on the A. O. Shirley Recreation Ground Grandstand. Completion of the Grandstand activity means that only the Lighting activity is left for completion at this stage, which will bring to a close the largest...
Monthly Report – October 2020

Monthly Report – October 2020

The October 2020 Monthly Report, produced by our Monitoring and Evaluation Team, contains status updates of projects during that month, as well as news on planning, policy and communications. Work continued in earnest on RDA implemented CDB projects, including the VG...