ELMORE STOUTT HIGH SCHOOL – IMMEDIATE IMPROVEMENTS | MUSIC CLASSROOMS
STATUS: COMPLETED
Ministry Partner: Ministry of Education, Culture, and Youth Affairs, Fisheries and Agriculture.
Project Number: 146 & 147
Project Start Date: May 2019
Projected End Date: August 2019
Duration: 3 months
Contractor: Import & Export Scaffolding & Services St. Lucia Ltd. | Autland Heavy Equipment Co. Ltd. | Sunleaf Construction | D. E. Property Development Ltd.
Funding Source: BVI Government | Unite BVI | BVI Alliance | Maples Group
BACKGROUND
Activity
Result
Renovation of 36 classrooms and a staff room, including repairs to the A/C, replacement of doors and installation of a new ceiling for improved sound control, lighting and electrical connections.
Four pre-fabricated modular classrooms have been installed on the ESHS campus. These will allow music lessons to resume in a sound-isolated space, with minimal disturbance to other students.
Junior High students have returned to ESHS and Senior High students continued to attend classes at CTL in much improved conditions that will ensure quality education is being delivered from September 2019.
Budget
$140,500 received as a donation from Maples Group. $250,000 Unite BVI contribution. $21,204 BVI Alliance. $255,965 Government of the VI.
Contributors
EVALUATING VALUE FOR MONEY
One of the core roles of the Recovery and Development Agency (RDA) is ensuring Value for Money (VfM) in the delivery of programmes and projects aimed toward recovery and development of the Virgin Islands.
ESHS Contracted Demolition
ESHS CTL Improvements
ESHS Temporary Classrooms
Please reach us at feedback@bvirecovery.vg or through our Contact Us page if you’d like to provide a donation to this project.