Project Update Highlights – July 2025 Monthly Report:
- Eslyn Henley Richiez Learning Centre: Internal works continued, including Mechanical, Electrical and Plumbing (MEP) installations and finishing works. The school is scheduled to open in early September 2025, as such practical completion is anticipated within the coming weeks.
- Water Optimisation: In July 2025, work continued in installing reservoir meters across the Territory. Additional meters are required to cover all required inflows and outflows at the selected reservoir sites, which has necessitated a variation in the project scope. These meters will improve tracking of water usage and facilitate early leak detection.
- BVI Health Services Authority Infrastructure Improvements: RDA issued an invitation to tender for the generator connectivity activity, with a bid submission deadline of 5th September. Works continued on the oxygen generator building, which is scheduled to be completed by the end of August 2025.
- Road Town Development Partnership: On 2nd July 2025, a public consultation for the Road Town Partnership project was held, at which schematics for the Road Town area were presented for public feedback. The RTP committee will further direct the project activities to be undertaken under the Partnership project. In July 2025, further planning for the initial walkway, sidewalks and roundabout activities continued.
- Farmers’ Reservoir: Following contract signature with Alvair Limited in May 2025, in July 2025 work continued on the engineering designs for the water mains and civil works on the Farmers’ Reservoir project. This has involved data gathering and technical discussions with the Ministry and the Water and Sewerage Department. The designs for the reservoir foundation will complement the designs for the water mains and civil works currently being prepared. This project is scheduled to be completed by October 2026.